Design and system integration for completely new RO/Ion Exchange water treatment facility.

BCI provided the design and system integration for completely new RO/Ion Exchange water treatment facility. Control panels, PLC programming, instrumentation and installation of equipment was provided by BCI.

Project was under budget and on schedule, bringing approximately $1.5 million back to Lee County.
Treatment Capacity increased from 9 million gallons per day (MGD) to 14 MGD of potable drinking water.

o Reverse Osmosis treatment production: 7.5 MGD
o Ion Exchange treatment production: 3.9 MGD
o Sandstone Aquifer blend production: 4.6 MGD
o 33 raw production wells with depths ranging from 40 feet to 870 feet